Home Bitcoin News Marathon Digital ‘Cautiously Optimistic’ About Meeting Early-2023 Hashrate Guidance as Delays Continue

Marathon Digital ‘Cautiously Optimistic’ About Meeting Early-2023 Hashrate Guidance as Delays Continue

by Valhalla Team
33 views



VMY5RTV2YNCG7EP5JAWCP45MZ4

About 4,200 Marathon miners were successfully installed in containers at one of Compute North’s new facilities in Texas, the company said in a statement. However, these mining rigs are now expected to come online in May, as opposed to its original schedule of April 17, as the company’s energy provider required additional consent from a third-party. Currently, it does not expect this process to impact future deployments of miners, the firm said in the statement.



Team Valhalla

Related Posts

Leave a Comment

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More